Working in partnership with Balfour Beatty Vinci, MPB is delivering all in-situ reinforced concrete works for the Bromford Tunnel West Portal and the Washwood Heath Retained Cut, including a series of highly complex internal structures.
The Bromford Tunnel West Portal will form a striking new gateway for HS2, guiding high speed trains in and out of Birmingham. This impressive structure reaches 22 m below ground, with a further 5 m deep drainage sump, requiring MPB to construct intricate reinforced concrete works at depths of up to 27 m. The portal seamlessly connects to a 750 m long retained cut, forming a critical section of the HS2 route.
MPB’s scope includes the delivery of 75,000 m³ of heavily reinforced concrete, from the portal headwall, designed to receive the TBM breakthrough, to nearly 1 km of complex base slab construction. This package showcases MPB’s capability to safely and efficiently deliver large scale, technically demanding reinforced concrete structures on one of the UK’s most ambitious infrastructure projects.
Services
Client
Balfour Beatty Vinci JV
Location
Birmingham
Sector