The Midland Metro Alliance engaged MPB under a formal Early Contractor Involvement (ECI) contract to support the development of the Delta Junction structure on Phase 1 of the Wednesbury to Brierley Hill Metro Extension.
Over the six-month ECI period, MPB worked collaboratively with the Alliance’s design and delivery teams to refine the design, optimise construction sequencing, and develop efficient, safe, and buildable methodologies for a highly constrained site located within a redundant railway corridor adjacent to a live tramway and operational depot.
Key contributions included:
Through this structured ECI process, MPB were able to validate the feasibility of the scheme, de-risk delivery, and refine the solution to meet the Midland Metro Alliance’s budgetary targets.