Working collaboratively, MPB led a comprehensive programme optimisation exercise, identifying and implementing a series of innovative buildability and sequencing improvements that reduced the delivery period from 60 weeks to just 43 weeks. Key measures included:
Through proactive planning, engineering innovation, and close integration with the BBV delivery team, MPB were able to derisk the programme and ensure the works were completed within the revised accelerated schedule.
Furthermore, MPB Structures received recognition at the esteemed CONSTRUCT Awards, where the company secured the ‘Best of the Sector’ award for its significant contribution to the Marston Box project.