Originally tendered as a 60-week programme, MPB completed the works in just 43 weeks, enabling BBV to meet the critical M42 closure date despite delays caused by National Highways approvals.
Throughout delivery, MPB worked closely with BBV and HS2, providing daily progress updates, contingency planning, and full technical support to ensure absolute confidence in programme and quality. This outstanding performance earned the project the CONSTRUCT 2023 Project of the Year Award.
Through every constraint and technical demand, MPB delivered with precision, pace, and total reliability, reinforcing our reputation for excelling on the most complex infrastructure challenges.